Masonry Begins as Framing Timeline Approaches

Construction at The Village at Providence Point continues to progress across structural, utility and site preparation phases as multiple crews work simultaneously across the site. Concrete foundations and columns continue to rise in several areas, with masonry work now underway on the health center.

Sewer, water and stormwater utility installations are progressing as backfilling and slab preparations continue. Third-party inspections remain ongoing for rebar, concrete and compaction work, with a welding inspection scheduled for next week.

Stream restoration work is progressing well as part of ongoing site improvements. Framing is targeted to begin in mid-July as structural elements near completion.

Additional construction updates will be shared as progress continues.

Tags:
Construction Progress
« Go Back

Schedule An  
APPOINTMENT

The opportunity to be part of senior living’s most extraordinary development in Annapolis, MD is available now — but you must act to take full advantage. Residences are filling fast. Reserve yours while there’s still a great selection available, and you can join your future neighbors in group gatherings and activities going on now.

SALES CENTER:
1997 Annapolis Exchange Pkwy, Suite 310, Annapolis, MD 21401
OFFICE HOURS:
8:30 a.m. - 5 p.m. Monday - Friday
Weekends by Appointment
443-782-3050

Campus
gallery

Explore interior and exterior renderings of  the campus.

See Renderings

UPCOMING
events

Attend an informational event to learn more.

Explore Events

FLOOR
PLANS

View Floor Plans

View our
apartment and
cottage homes.

join the
charter club

Learn How

Discover the
benefits of
reserving now!

SIGN UP TO RECEIVE EMAIL UPDATES